Document Community Services 2024/25 Service Area Plan Quarter 1 Update

Community Services 2024/25 Service Area Plan Quarter 1 Update

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decisions:

The Committee reviewed progress with the Community Services Service Area Plan 2024/25 Quarter 1 Update.

 

Officers advised that the Business Centre was on target to complete all of its primary objectives for the year with a greater level of detail in the Appendix to the report on key projects and areas of work.  Some of the completed objectives included the review of Community Transport, completion of the Section 11 Children Safeguarding Audit, the Play Space Improvement Programme, the procurement of a Disabled Adaptions Works Contractor and the launch of the Runnymede Sports Forum. 

 

A number of projects were in progress and some had not yet started as they relied on other factors including input from colleagues in other business centres such as Assets and Regeneration and Finance.

 

It was confirmed that all the SANG Management Plans had been written in draft and Officers agreed to provide Councillors with an update on the draft SANG for Hare Hill Open Space when it was available.

 

The report was duly noted.

Report author: Darren Williams

Publication date: 01/10/2024

Date of decision: 19/09/2024

Decided at meeting: 19/09/2024 - Community Services Committee